Progress continues to move at a rapid pace as the team readies for the coming winter weather. This has been the week for a lot of underground work. The plumbing and electrical have been installed underground in most areas of the building. DTE has been on-site installing new underground wiring to nearby buildings. A storm sewer system is going in beginning at Hannan Road and heading east. Steel structural work has been completed in the ground and a concrete floor poured over much of the footprint of the building. The nature trails are moving along. Carpenters have begun work installing bridges across the wetlands on the path.
| From the South End (Week 5) |
| From the North End (Week 5) |
| Concrete Floor Poured |
| Storm Sewer Being Installed |
| Bridges over wetlands begun on Nature Trail |