Half Way There!

This week we saw amazing progress.  Four months into the expansion and we are half way done with the whole project and the building is now 35% complete!  This week storm lines were installed inside the building between the laundry and activities rooms.  We also saw installation of the first head wall panel that will house the in-wall respiratory equipment.  Carpenters were hard at work outside too with the framing of the carport at the main entrance.

The main entrance with a nice view of the newly constructed carport


The carport


Hello reception!



Looking out of the 3-season room to the courtyard


The dining room



The view from a client room. NICE!