Friday, March 11, 2011

Spring's In the Air

Spring must be in the air, because things at the new NCC are starting to bloom.  Inside, the nurses' station is taking shape and the first coats of paint have been rolled out. Outside we're seeing shingles make their home on the rest of the roof and brick laid. Not too bad for a week's work!


A view of a client room

Brick is laid at the base of the building

The nurses' station


Friday, March 4, 2011

Slow and Steady Wins the Race

We keep moving forward with the new NeuroCare Center. This week drywall was taped and later primed. Now, many of the interior walls are ready for paint.  So roll up those sleeves and put out some paint rags- we’re ready to roll (some paint!)

Walls are primed in preparation of paint in the new service corridor

Drywall being taped... check out that view!